Connecting activity pairs and standard time series

With the demand model of the tour-based model type you can calculate the OD demand even by the hour; therefore you need to connect the standard time series as percentages with activity pairs and person groups (Properties and options of standard time series).

1.  In the Demand menu, click the Demand models entry.

The Demand models window opens.

2.  Select the Activity pairs tab.

3.  In the Select demand model list, click the demand model of your choice.

4.  In the list, select the activity pair you would like to combine with standard time series and person groups.

5.  In the Time series column, click the corresponding button.

The Select time series window opens.

6.  Make the desired changes.

Element

Description

The same time series for all person groups

If this option has been selected, the same standard time series is allocated to all person groups. From the selection list, you can select the standard time series.

Separate time series per person group

If this option has been selected, you can select a specific standard time series for each person group; therefore, you need to mark the desired person group in the list and select the standard time series from the particular selection list in the Time series column.

7.  Confirm with OK.

Allocation is applied.